The '''three-point estimation''' technique is used in management and [[information systems]] applications for the construction of an approximate [[probability distribution]] representing the outcome of future events, based on very limited information. While the distribution used for the approximation might be a [[normal distribution]], this is not always so. For example, a [[triangular distribution]] might be used, depending on the application.
In three-point estimation, three figures are produced initially for every distribution that is required, based on prior experience or best-guesses:
* ''a'' = the best-case estimate
* ''m'' = the most likely estimate
* ''b'' = the worst-case estimate
These are then combined to yield either a full probability distribution, for later combination with distributions obtained similarly for other variables, or summary descriptors of the distribution, such as the [[mean]], [[standard deviation]] or [[percentile|percentage points]] of the distribution. The accuracy attributed to the results derived can be no better than the accuracy inherent in the three initial points, and there are clear dangers in using an assumed form for an underlying distribution that itself has little basis.
==Estimation==
Based on the assumption
: ''E'' = (''a'' + 4''m'' + ''b'') / 6
: SD = (''b'' − ''a'') / 6
''E'' is a [[weighted average]] which takes into account both the most optimistic and most pessimistic estimates provided. SD measures the variability or uncertainty in the estimate.
In
The [[triangular distribution]] is also commonly used. It differs from the [[Double-triangular distribution|double-triangular]] by its simple triangular shape and by the property that the mode does not have to coincide with the median. The mean (
: ''E'' = (''a'' + ''m'' + ''b'') / 3.
In some applications,<ref name=MOD2007>Ministry of Defence (2007) [http://www.aof.mod.uk/aofcontent/tactical/risk/downloads/3pepracgude.pdf "Three point estimates and quantitative risk analysis"] [http://www.aof.mod.uk/aofcontent/tactical/risk/content/tpe.htm Policy, information and guidance on the Risk Management aspects of UK MOD Defence Acquisition]</ref> the triangular distribution is used directly as an estimated [[probability distribution]], rather than for the derivation of estimated statistics.
==Project management==
To produce a project estimate the project manager:
* Decomposes the project into a list of estimable tasks, i.e. a [[work breakdown structure]]
* Estimates
* Calculates the
* Calculates the
The E and SD values are then used to convert the project time estimates to [[confidence
*
*
*
*
*
These confidence
==
* [[Five-number summary]]
* [[Seven-number summary]]
* [[Program Evaluation and Review Technique]] (PERT)
{{More footnotes|date=September 2010}}
{{DEFAULTSORT:Three-Point Estimation}}▼
[[Category:Statistical approximations]]▼
==References==
{{Reflist}}
{{Project cost estimation methods}}
▲{{DEFAULTSORT:Three-Point Estimation}}
▲[[Category:Statistical approximations]]
[[Category:Informal estimation]]
|