{{Short description|Class of computational problem}}
[[File:Flow Shop Ordonnancement.JPEG|thumb|Flow Shop Ordonnancement]]
'''Flow-shop scheduling''' is an [[optimization problem]] in [[computer science]] and [[Operations Research|operations research]]. It is a variant of [[optimal job scheduling]]. In a general job-scheduling problem, we are given ''n'' jobs ''J''<sub>1</sub>, ''J''<sub>2</sub>, ..., ''J<sub>n</sub>'' of varying processing times, which need to be scheduled on ''m'' machines with varying processing power, while trying to minimize the [[makespan]] – the total length of the schedule (that is, when all the jobs have finished processing). In the specific variant known as ''flow-shop scheduling'', each job contains exactly ''m'' operations. The ''i''-th operation of the job must be executed on the ''i''-th machine. No machine can perform more than one operation simultaneously. For each operation of each job, execution time is specified.
Flow-shop scheduling is a special case of [[job-shop scheduling]] where there is strict order of all operations to be performed on all jobs. Flow-shop scheduling may apply as well to [[Manufacturing|production]] facilities as to [[computing]] designs. A special type of flow
In the standard [[Optimal job scheduling|three-field notation for optimal-job-scheduling problems]], the flow-shop variant is denoted by '''F''' in the first field. For example, the problem denoted by " '''F3|<math>p_{ij}</math>|'''<math>C_\max</math>" is a 3-machines flow-shop problem with unit processing times, where the goal is to minimize the maximum completion time.
==Formal definition==
Operations within one job must be performed in the specified order. The first operation gets executed on the first machine, then (as the first operation is finished) the second operation on the second machine, and so on until the
==Sequencing
The sequencing problem can be stated as determining a sequence S such that one or several sequencing objectives are optimized.
# (Average) Flow time, <math>\sum (w_i) F_i </math>
# Makespan, C<sub>max</sub>
# (Average) Tardiness, <math>\sum (w_i) T_i </math>
# ....
detailed discussion of performance measurement can be found in [[Behnam Malakooti|Malakooti]](2013).<ref name=Malakooti>Malakooti, B (2013). Operations and Production Systems with Multiple Objectives. John Wiley & Sons. {{ISBN|978-1-118-58537-5}}.</ref>
==Complexity of flow shop scheduling==▼
As presented by Garey et al. (1976), most of extensions of the flow shop scheduling problems are NP-Hard and few of them can be solved optimally in O(nlogn), for example F2|prmu|C<sub>max</sub> can be solved optimally by using [[Johnson's Rule]].▼
==Solution Methods==▼
As presented by Garey et al. (1976),<ref name=Garey>{{cite journal
The proposed methods to solve flow shop scheduling problems can be classified as [[exact algorithm]] such as [[Branch and Bound]] and [[Heuristic algorithm]] such as [[genetic algorithm]].▼
| last1=Garey | first1=M. R.
=== Minimizing makespan,C<sub>max</sub> ===▼
| last2=Johnson | first2=D. S.
F2|prmu|C<sub>max</sub> and F3|prmu|C<sub>max</sub> can be solved optimally by using Johnson's Rule (1954) but for general case there is no algorithm that guarantee the optimality of the solution.<br>▼
| last3=Sethi | first3=Ravi
| date=1976
The flow shop contains n jobs simultaneously available at time zero and to be processed by two machines arranged in series with unlimited storage in between them. The processing time of all jobs are known with certainty. It is required to schedule n jobs on machines so as to minimize makespan. The Johnson's rule for scheduling jobs in two machine flow shop is given below:▼
| title=The complexity of flowshop and jobshop scheduling
In an optimal schedule, job i precedes job j if ''min{p<sub>i1</sub>,p<sub>j2</sub>} < min{p<sub>j1</sub>,p<sub>i2</sub>}''. Where as, p<sub>i1</sub> is the processing time of job i on machine 1 and p<sub>i2</sub> is the processing time of job i on machine 2. Similarly, p<sub>j1</sub> and p<sub>j2</sub> are processing times of job j on machine 1 and machine 2 respectively.<br>▼
| journal=[[Mathematics of Operations Research]]
| volume=1
| issue=2
p<sub>1j</sub>=processing time of job j on machine 1<br>▼
| pages=117–129
p<sub>2j</sub>=processing time of job j on machine 2▼
▲
| last1=Johnson
| date=1954
Step 1:Form set1 containing all the jobs with p<sub>1j</sub> < p<sub>2j</sub> <br>▼
| title=Optimal two-and three-stage production schedules with setup times included
Step 2:Form set2 containing all the jobs with p<sub>1j</sub> > p<sub>2j</sub>,the jobs with p<sub>1j</sub>=p<sub>2j</sub> may be put in either set.<br>▼
| journal=Naval Research Logistics Quarterly
Step 3: Form the sequence as follows:<br>▼
| volume=1
i) The job in set1 go first in the sequence and they go in increasing order of p<sub>1j</sub>(SPT)<br>▼
| issue=1
ii) The jobs in set2 follow in decreasing order of p<sub>2j</sub> (LPT). Ties are broken arbitrarily.<br>▼
| pages=61–68
This type schedule is referred as SPT(1)-LPT(2) schedule.▼
| doi=10.1002/nav.3800010110}}</ref>
The detailed discussion of the available solution methods are provided by Malakooti (2013).▼
▲The proposed methods to solve flow
▲=== Minimizing makespan, C<sub>max</sub> ===
▲F2|prmu|C<sub>max</sub> and F3|prmu|C<sub>max</sub> can be solved optimally by using [[Johnson's Rule]]<ref
▲The flow shop contains n jobs simultaneously available at time zero and to be processed by two machines arranged in series with unlimited storage in between them. The processing time of all jobs are known with certainty. It is required to schedule n jobs on machines so as to minimize makespan. The Johnson's rule for scheduling jobs in two
▲In an optimal schedule, job i precedes job j if ''min{p<sub>
For Johnson's algorithm:
Johnson's algorithm:
▲
▲#: (i) The job in set1 go first in the sequence and they go in increasing order of p<sub>1j</sub> (SPT)
▲#: (ii) The jobs in set2 follow in decreasing order of
▲
==See also==
* [[Open-shop scheduling]]
* [[Job-shop scheduling]]
==References==
{{Reflist}}