Three-point estimation: Difference between revisions

Content deleted Content added
Addbot (talk | contribs)
m Bot: Migrating 2 interwiki links, now provided by Wikidata on d:q1256911
rmv promotional external link
 
(34 intermediate revisions by 31 users not shown)
Line 1:
{{Short description|Technique used in management and information systems}}
The '''three-point estimation''' technique is used in management and [[information systems]] applications for the construction of an approximate [[probability distribution]] representing the outcome of future events, based on very limited information. While the distribution used for the approximation might be a [[normal distribution]], this is not always so. and, forFor example, a [[triangular distribution]] might be used, depending on the application.,<ref name=MOD2007>Ministry of Defence (2007) [http://www.aof.mod.uk/aofcontent/tactical/risk/downloads/3pepracgude.pdf "Three point estimates and quantitative risk analysis"] [http://www.aof.mod.uk/aofcontent/tactical/risk/content/tpe.htm Policy, information and guidance on the Risk Management aspects of UK MOD Defence Acquisition]</ref>
 
In three-point estimation, three figures are produced initially for every distribution that is required, based on prior experience or best-guesses:
* ''a'' = the best-case estimate
* ''m'' = the most likely estimate
* ''b'' = the worst-case estimate.
These are then combined to yield either a full probability distribution, for later combination with distributions obtained similarly for other variables, or summary descriptors of the distribution, such as the [[mean]], [[standard deviation]] or [[percentile|percentage points]] of the distribution. The accuracy attributed to the results derived can be no better than the accuracy inherent in the 3three initial points, and there are clear dangers in using an assumed form for an underlying distribution that itself has little basis.
 
==Estimation==
Based on the assumption (possibly unwarranted) that a ''double''-[[triangularPERT distribution]] governs the data, several estimates are possible. These values are used to calculate an ''E'' value for the estimate and a [[standard deviation]] (SD) as [[L-estimator]]s, where:
 
: ''E'' = (''a'' + 4''m'' + ''b'') / 6
Line 14 ⟶ 15:
 
''E'' is a [[weighted average]] which takes into account both the most optimistic and most pessimistic estimates provided. SD measures the variability or uncertainty in the estimate.
In ProjectProgram Evaluation and Review Techniques ([[PERT]]) the three values are used to fit a [[BetaPERT distribution]] for [[Monte Carlo simulations.{{Citation neededMethod|date=SeptemberMonte 2010}}Carlo]] simulations.
 
The [[triangular distribution]] is also commonly used. It differs from the [[Double-triangular distribution|double-triangular]] by its simple triangular shape and by the property that the mode does not have to coincide with the median. The mean (expectation[[expected value]]) is then:
 
: ''E'' = (''a'' + ''m'' + ''b'') / 3.
 
In some applications,<ref name=MOD2007>Ministry of Defence (2007) [http://www.aof.mod.uk/aofcontent/tactical/risk/downloads/3pepracgude.pdf "Three point estimates and quantitative risk analysis"] [http://www.aof.mod.uk/aofcontent/tactical/risk/content/tpe.htm Policy, information and guidance on the Risk Management aspects of UK MOD Defence Acquisition]</ref> the triangular distribution is used directly as an estimated [[probability distribution]], rather than for the derivation of estimated statistics.
 
==Project management==
To produce a project estimate the project manager:
* Decomposes the project into a list of estimable tasks, i.e. a [[work breakdown structure]]
* Estimates the Eexpected value E(task) and the [[standard deviation]] SD(task) of this estimate for each task. time
* Calculates the Eexpected value for the total project work time as <math>\operatorname{E }(Project Work\text{project}) = Σ\sum{ \operatorname{E }(Task\text{task})}</math>
* Calculates the SD value SD(project) for the standard error of the estimated total project work time as: SD<math> \operatorname{SD}(Project Work\text{project}) = √(Σ \sqrt{\sum{\operatorname{SD }(Task\text{task}) <sup>^2}}</supmath>) under the assumption that the project work time estimates are [[correlation|uncorrelated]]
 
The E and SD values are then used to convert the project time estimates to [[confidence levelsinterval]]s as follows:
 
* ConfidenceThe level68% inconfidence Einterval valuefor +/-the SDtrue project work time is approximately 68%E(project) ± SD(project)
* The 90% confidence interval for the true project work time is approximately E(project) ± 1.645 &times; SD(project)
* Confidence level in E value +/- 1.645 &times; SD is approximately 90%
* ConfidenceThe level95% inconfidence Einterval valuefor +/-the 2true &times;project SDwork time is approximately 95%E(project) ± 2 &times; SD(project)
* ConfidenceThe level99.7% inconfidence Einterval valuefor +/-the 3true &times;project SDwork time is approximately 99.7%E(project) ± 3 &times; SD(project)
* Information Systems typically useuses the 95% confidence level, i.e. E Value + 2&nbsp;&times;&nbsp;SD,interval for all project and task estimates.<ref>http://en[[68–95–99.wikipedia.org/wiki/68-95-99.7_rule7 rule]]</ref>
 
These confidence levelinterval estimates assume that the data from all of the tasks combine to be approximately normal (see [[Asymptotic distribution#Asymptotic normality|asymptotic normality]]). Typically, there would need to be 20&ndash;30 tasks for this to be reasonable, and each of the estimates E for the individual tasks would have to be unbiased.
 
==See also==
Line 49 ⟶ 50:
{{Reflist}}
 
{{Project cost estimation methods}}
==External links==
*[http://www.visionarytools.com/decision-making/3-point-estimating.htm It Takes Three to Make Good Estimates] from Visionary Tools
*[http://www.super-business.net/Quantitative-Methods/1055.html Three-Point Estimate Approximations] from www.super-business.net
*[http://www.4pm.com/articles/PERT_program_evaluation_&_review_technique.pdf Risk and duration estimates: 3 point estimating] from www.4pm.com
 
{{DEFAULTSORT:Three-Point Estimation}}
[[Category:Statistical approximations]]