* The 95% confidence interval for the true project work time is approximately E(project) ± 2 × SD(project)
* The 99.7% confidence interval for the true project work time is approximately E(project) ± 3 × SD(project)
* Information Systems typically uses the 95% confidence interval for all project and task estimates.<ref>[[
These confidence interval estimates assume that the data from all of the tasks combine to be approximately normal (see [[Asymptotic distribution#Asymptotic normality|asymptotic normality]]). Typically, there would need to be 20–30 tasks for this to be reasonable, and each of the estimates E for the individual tasks would have to be unbiased.
|