===Bid failure===
The Transbus specification requirement led three transit agencies{{efn|name=79bid}} to request bids for a joint procurement of 530 buses in January 1979.<ref name=Reason-80/> It was estimated that a single Transbus would cost 60% more than a comparable New Look bus, driven mainly by the low-floor requirement, which in turn would require significant
By March 1979, [[Grumman]] Flxible{{efn|[[Grumman]] acquired [[Flxible]] from [[Rohr, Inc.|Rohr]] on January 3, 1978 for {{USD|55000000|1978|round=-4}}. The acquisition included two hand-built prototypes of and the design for the [[Flxible Metro|Model 870]].<ref name=GrummanVRohr>{{cite court |vol=748 |reporter=F.2d |opinion=729 |court=[[United States Court of Appeals, Second Circuit|2d Cir.]] |date=1984 |litigants=Grumman Allied Industries, Inc. v. Rohr Industries, Inc. |url=https://casetext.com/case/grumman-allied-industries-v-rohr-industries}}</ref>}} announced it did not intend to bid on the new contract, and GM stated it was unlikely to bid. The president of Grumman Flxible, Thomas J. Bernard, said that internal estimates put the bid price at {{USD|230000|1979|round=-3}} per bus, nearly double the {{USD|120000|1979|round=-3}} cost per conventional New Look bus, and added the Department of Transportation "has been seeking a more productive bus. We believe that a bus that weighs more, gets fewer miles per gallon, has fewer seats and less standing room is not a more productive bus."<ref>{{cite news |url=https://www.newspapers.com/newspage/147073438/ |title=Lack Of Bids Threatens 'Wheelchair' Bus |date=March 14, 1979 |newspaper=The Pittsburgh Press |accessdate=9 October 2020}}</ref> Flxible also stated that component suppliers (such as [[Rockwell International]], who built transit bus axles) would need federal support to develop the new technologies needed for Transbus, as the limited transit bus market meant most component suppliers were unwilling to develop them.<ref name=UMTA-oversight-hearing/>{{rp|114}}
|