=== Example ===
In the following example there are seven tasks, labeled ''A'' through ''G''. Some tasks can be done concurrently (''A'' and ''B'') while others cannot be done until their predecessor task is complete (''C'' cannot begin until ''A'' is complete). Additionally, each task has three time estimates: the optimistic time estimate (''o''), the most likely or normal time estimate (''m''), and the pessimistic time estimate (''p''). The expected time (''te'') is computed using the formula (''o'' + 4''m'' + ''p'') ÷ 6.{{sfn|Kerzner|2009}}{{rp|512-513}}
{| class="wikitable"
|