PERT offers a management tool,{{sfn|Kerzner|2009}}{{rp|497}} which relies "on arrow and node diagrams of ''activities'' and ''events'': arrows represent the ''activities'' or work necessary to reach the ''events'' or nodes that indicate each completed phase of the total project."<ref name="MB 1968" />
PERT and CPM are complementary tools, because "CPM employs one time estimation and one cost estimation for each activity; PERT may utilize three time estimates (optimistic, expected, and pessimistic) and no costs for each activity. Although these are distinct differences, the term PERT is applied increasingly to all critical path scheduling."<ref name="MB 1968" />
|