Content deleted Content added
No edit summary |
|||
Line 11:
: ''E'' = (''a'' + 4''m'' + ''b'') / 6
: SD = (''b'' − ''a'') / 6
''E'' is a [[weighted average]] which takes into account both the most optimistic and most pessimistic estimates provided. SD measures the variability or uncertainty in the estimate.
Line 27:
* Estimates the E value and SD for each task.
* Calculates the E value for the total project work as E (Project Work) = Σ E (Task)
* Calculates the SD value for the total project work as SD (Project Work) =
The E and SD values are then used to convert the project estimates to confidence levels as follows:
|