Content deleted Content added
→Sources: +1 |
→Day-ahead operation: revised statement, added source |
||
Line 17:
* demand-supply balance need to be maintained, including the sufficient [[spinning reserve]]s for contingency. The balance need to reflect the transmission constraints;
* thermal units might have limits on minimum uptime (once switched on, cannot be turned off quickly) and downtime (once stopped, cannot be quickly restarted again);
* "must-run" units have to run due to technical constraints (for example, [[combined heat and power]] plants must run if their heat is needed);
* there is usually a
== Hours-ahead operation ==
|