Line 213:
Therefore, activity ''b'' can be delayed almost 4 work days without delaying the project. Likewise, activity ''d'' '''or''' activity ''f'' can be delayed 4.68 work days without delaying the project (alternatively, ''d'' and ''f'' can be delayed 2.34 work days each).
===Avoiding loops===
|