Line 213:
Therefore, activity ''b'' can be delayed almost 4 work days without delaying the project. Likewise, activity ''d'' '''or''' activity ''f'' can be delayed 4.68 work days without delaying the project (alternatively, ''d'' and ''f'' can be delayed 2.34 work days each).
 
:[[File:pert example network diagram visio.gif|thumb|800pxframe|leftcenter|A completed network diagram created using [[Microsoft Visio]]. Note the [[critical path method|critical path]] is in red.]]
{{Clear}}
 
===Avoiding loops===