Slack/[[Float (project management)|Float]]: Determines the duration of activity delay that the project can tolerate before the project comes in late. The difference between the earliest and the latest start time.{{sfn|Kerzner|2009}}{{rp|502}}{{sfn|Sanghera|2019}}{{rp|183}} i.e. Slack = latest start date - earliest start day or Slack = latest finish time - earliest finish time.
 
Any activities which have a slack of 0, they are on the [[Critical path method|critical path]].