Project timeline: The cited source has been modified to show that the testimony is no longer upcoming but was presented on 7 May 2024. Change the article accordingly.
Line 91:
In August 2023, Bollinger Shipyards began steel cutting for eight "prototype modules" for the first Polar Security Cutter.<ref>{{cite web|url=https://news.usni.org/2023/08/09/bollinger-cuts-first-steel-on-polar-security-cutter-polar-sentinel|title=Bollinger Cuts First Steel on Polar Security Cutter|date=9 August 2023|accessdate=10 August 2023|publisher=USNI News}}</ref>
 
InOn April7 May 2024, the [[Congressional Budget Office]]'s upcoming testimony before the Subcommittee on Transportation and Maritime Security Committee on Homeland Security estimated that the total cost of three vessels would be $5.1 billion, about 60% more than the Coast Guard's estimate in March 2024, and the delivery of the first vessel would be in 2029.<ref name="cbo_april2024" />
 