Caltrain Express Program: Difference between revisions

Content deleted Content added
No edit summary
No edit summary
Line 28:
 
==History==
In 1997, after plans to extend [[Caltrain]] to downtown [[San Francisco]] were put on hold, the Peninsula Corridor Joint Powers Board (PCJPB) started the ''Rapid Rail Study'', which was published as a draft in October 1998.<ref name=98RRS>{{cite report |url=http://bayrailalliance.org/files/library/Caltrain_RRP_draft.pdf |title=Draft Caltrain Rapid Rail Study |date=1 October 1998 |publisher=Peninsula Corridor Joint Powers Board |accessdate=29 March 2017 |archive-url=https://web.archive.org/web/20110807145542/http://bayrailalliance.org/files/library/Caltrain_RRP_draft.pdf |archive-date=7 August 2011 |url-status=live }}</ref> The 1998 ''Rapid Rail Study'' prioritized planned capital improvements to implement the 1997 ''Caltrain 20-Year Strategic Plan'', which sought to improve service and increase ridership, which was assumed to correspond directly to improved service (through decreased transit times and increased train frequencies). The highest-priority projects were intended to rehabilitate the line to "reverse decades of deferred maintenance" and enhance the line by adding [[passing loop|overtake tracks]] to implement express service.<ref name=98RRS /><ref name=99RRSIP /> After rehabilitation and enhancement, the ''Rapid Rail Study'' called for [[Caltrain Modernization ProjectProgram|electrification of the line]].<ref name=98RRS />
 
Proposed rehabilitation work included rebuilding tracks and grade crossings to enable Caltrain to raise the systemwide speed limit to {{convert|79|to|90|mph|abbr=on}} and replacing bridges, culverts, and signals.<ref name=98RRS /> The initial enhancement projects included adding third overtake tracks in Burlingame (between the stations at Millbrae and San Mateo, for northbound trains) and San Mateo (between 9th Avenue and Hillsdale, for southbound trains) to allow express trains to pass slower all-stop local trains, and adding a third [[pocket track|turnback track]] in Palo Alto to allow more frequent short-line service.<ref name=98RRS /> In 1999, PCJPB published an implementation plan for the ''Rapid Rail Study'' which called for a $280&nbsp;million investment from the three counties served by Caltrain.<ref name=99RRSIP>{{cite report |url=http://bayrailalliance.org/files/library/Caltrain_RRP_implementation_plan.pdf |title=Caltrain Rapid Rail Study Implementation Plan |date=1999 |publisher=Peninsula Corridor Joint Powers Board |accessdate=29 March 2017 |archive-url=https://web.archive.org/web/20110807145429/http://bayrailalliance.org/files/library/Caltrain_RRP_implementation_plan.pdf |archive-date=7 August 2011 |url-status=live }}</ref>