Line 25:
(I'm not sure if the "early finish" and "late start" boxes were this or the other way round.)
-- [[User:Smjg|Smjg]] 16:14, 31 Mar 2005 (UTC)
 
[PDG] My long standing question is WHY are the early start and early finish dates invariably shown ABOVE the late start and late finish dates, when in fact, this makes no sense mathematically as we are supposed to DEDUCT the early dates FROM the late dates, resulting in the Total Float (or Total Slack) Thus what is shown here is logically exactly opposite and thus counterintuitive to what should be.
 
BR,
Dr. PDG, Jakarta
[[User:Dr PDG|Dr PDG]] ([[User talk:Dr PDG|talk]]) 08:38, 27 October 2008 (UTC)
 