The '''three-point estimation''' technique is based on statistical methods, and in particular, the [[normal distribution]]. Three-point estimation is the preferred estimation technique for [[information systems]] (IS) projects. In the three-point estimation there are three figures produced for every estimate:
Line 29 ⟶ 27:
* Confidence level in E value + 2 × SD is approximately 95%
* Confidence level in E value + 3 × SD is approximately 99.5%
* IS{{
These confidence level estimates assume that the data from all of the tasks combine to be approximately normal (see [[Asymptotic distribution#Asymptotic normality|asymptotic normality]]). Typically, there would need to be 20–30 tasks for this to be reasonable, and each of the estimates E for the individual tasks would have to be unbiased.
Line 38 ⟶ 36:
* [[Triangular distribution]]