===Major Components of the Project===
All the phases are carried out in parallel and expected to be completed by 2015.
==== Port component ====
 
====Phase-1: Construction of Port at Sittwe ====
* Construction of an integrated Port & Inland Water Transport (IWT) terminal at [[Sittwe]] including [[Dredging]]. As of Nov 2014, construction of integrated Port cum IWT jetty at Sittwe is substantially completed.
* Phase One is the construction of jetties and a port facility at integrated Port & Inland Water Transport (IWT) terminal at [[Sittwe]] in [[Arakan]] state of [[Myanmar]]. The [[Inland Waterways Authority of India]] (IWAI) and [[Essar Group|ESSAR Projects Ltd]] are the implementing partners, and the estimated completion date is June 2014. Construction of integrated Port cum [[Inland navigation|Inland Water Transport (IWT)]] jetty at [[Sittwe]] [[Port|seaport]] is substantially completed.
 
==== Inland Water Transport (IWT) components ====
* Development of navigational channel along [[Kaladan River]] from [[Sittwe]] to [[Paletwa]] (158 km). Dredging by [[Myanmar]] govt started in Feb 2014.
 
==== Phase-2: Inland Water Transport (IWT) components ====
* Development of navigational channel for cargo ships ([[Barrage]]s) along [[Kaladan River]] from [[Sittwe]] to [[Paletwa]] (158 km). The [[Inland Waterways Authority of India]] (IWAI) and [[Essar Group|ESSAR Projects Ltd]] are the implementing partners. Dredging by [[Myanmar]] govt started in Feb 2014.
* Construction of an ""[[Inland navigation|Inland Water Transport (IWT)]] to Road Highway"" transhipment terminal at [[Paletwa]]. As of 2014 Nov, this is mostly completed.
* Construction of 6 IWT [[Barge]]s (300 Ton capacity) for transportation of cargo between [[Sittwe]] and [[Paletwa]]. This work commenced at [[Yangon]] in Feb 2013.
 
====Phase-3 Highway within Myanmar====
* Construction of 6 IWT [[Barge]]s (300 Ton capacity) for transportation of cargo between [[Sittwe]] and [[Paletwa]]. This work commenced at [[Yangon]] in Feb 2013.
* Construction of a road highway from [[Paletwa]] to India-Myanmar border for 110 km by [[IRCON International]] is The construction of stretch / component of road in Myanmar is being arranged by MEA and it will have a separate Project Development Consultant. Phase Three is the construction of a 130 km two-lane highway from [[Paletwa]] town to the Myanmar-India border crossing at [[MyeikWa]]/[[Lomasu]]. The Burma Ministry of Construction and Burmese construction company Max Myanmar Group of Companies are the implementing partners for the road construction in [[Paletwa]] township, and the estimated completion date is 2015.
 
====Phase-4: Highway componenton Indian side====
* ConstructionPhase Four is the construction of a road100 km two-lane highway in [[Mizoram]] State from [[PaletwaLomasu]] to India-Myanmar[[Lawngtlai]], borderat forwhich 110point kmit bywill connect with the existing [[IRCONNational InternationalHighway 54 (India)]] is(NH The54). Phase four also includes the construction of stretcha /Land componentCustoms ofStation road(LCS) at [[Zorinpui]] in Myanmar[[Mizoram]] isState. beingThe arrangedIndian by[[Ministry MEAfor Development of North Eastern Region]], the [[Mizoram]] State Public Works Department and itlocal willcontractors haveRam aDayal separateSharma Projectand DevelopmentARSS-Atlanta are the implemention partners, and the estimated completion date is early Consultant2014. The Border to NH.[[National Highway 54 (LawngtlaiIndia)]] Road(NH 54) at [[Lawngtlai]] road on Indian side in Mizoram is in progress and under the overall control of Ministry of Road Transport and Highways, Govt. of India.
 
===Framework for Project Implementation===