Line 10:
* late finish date
* duration
* activity name
* WBS reference
Slack/Float: Determines the duration of activity delay that the project can tolerate before the project comes in late. The difference between the earliest and the latest start time. i.e. Slack = last start date - early start day or Slack = last finish time - early finish time.
Any activities which have a slack of 0, they are on the critical path.
[[File:TinhSoDoMangPDM.png|thumbnail|right|solving the PDM, with: BS is an early start date. BM is a late start date. KS is an early finish date. KM is a late finish date.]]
|