'''Evidence-based
==Including all time spent==
One of the core ideas of
Most people, when estimating, measure the time they actually spend on a project
However, recording and attempting to
The key insight in
The appeal of this idea is simplicity
==Monte Carlo
Another core idea is the use of the [[Monte Carlo method]] to predict project completion dates. This method evaluates how reliable previous estimates have been. Instead of a single completion date, the method results in multiple possible completion dates, each with an associated probability of being correct.
|