Content deleted Content added
ClueBot NG (talk | contribs) m Reverting possible vandalism by 62.255.8.170 to version by Kuru. Report False Positive? Thanks, ClueBot NG. (3473715) (Bot) |
|||
Line 6:
==Usage==
ADM is used for scheduling activities in a [[project plan]]. Precedence relationships between activities are represented by circles connected by one or more arrows. The length of the arrow represents the duration of the relevant activity. ADM only shows finish-to-start relationships, meaning that each activity is completed before the successor activity starts. Declan Jones
Sometimes a "dummy task" is added, to represent a dependency between tasks, which does not represent any actual activity. The dummy task is added to indicate precedence that can't be expressed using only the actual activities. Such a dummy task often has a completion time of 0.
|