Three-point estimation

This is an old revision of this page, as edited by Michael Hardy (talk | contribs) at 17:09, 21 February 2009 (started cleanup. more work is needed.). The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.

You must add a |reason= parameter to this Cleanup template – replace it with {{Cleanup|reason=<Fill reason here>}}, or remove the Cleanup template.

The three-point estimation technique is based on statistical methods, and in particular, the normal distribution. Three point estimation is the preferred estimation technique for IS projects[What is "IS"??]. In three-point estimation we produce three figures for every estimate:

  • a = the best case estimate
  • m = the most likely estimate
  • b = the worst-case estimate

These values are used to calculate an E value for the estimate and a standard deviation (SD) where:

E = a + 4m + b / 6
SD = (b − a)/6

E is a weighted average which takes into account both the most most optimistic and pessimistic estimates provided and SD measures the variability or uncertainty in the estimate.

To produce a project estimate the project manager:

  • Decomposes the project into a list of estimable tasks, i.e. a Work Breakdown Structure
  • Estimates each the E value and SD for each task.
  • Calculates the E value for the total project work as E (Project Work) = Σ E (Task)
  • Calculates the SD value for the total project work as SD (Project Work) = √Σ SD (Task) 2

We then use the E and SD values to convert the project estimates to Confidence Levels as follows:

  • Confidence level in E value is approximately 50%
  • Confidence level in E value + SD is approximately 70%
  • Confidence level in E value + 2 × SD is approximately 95%
  • Confidence level in E value + 3 × SD is approximately 99.5%
  • IS use the 95% confidence level, i.e. E Value + 2 × SD, for all project and task estimates [What is "IS"???]